Breakstone top coat and asphalt layers construction within the project “Infrastructure development in “Krievu sala” to shift port activities from the center of Riga, Latvia.”

Construction time – from May 11 to August 14, 2015. The following major works have been accomplished:

  • construction of hot asphalt subcoating (ACb32, h= 9cm),
  • construction of hot asphalt linking layer (ACb22, h= 6cm),
  • construction of hot asphalt top layer (AC16, h= 5cm),
  • laying of breakstone top coat (fr.0/45, h=10cm).